day 216: concrete
formwork for the concrete front porch and steps
here comes the concrete truck
pouring the front porch
the concrete team
apparently a good time to smoke a pipe is when you are spreading concrete
the front porch after some floating and broom sweeping
before the concrete came, the guys made formwork for the wall footings
bringing over the concrete block
laying concrete block where it won't be seen
the excavator helps build up the ground
what's wrong with this picture?
the dirt pile's biggest fan
day 1 progress on the stone walls
terraced walls are dry-stacked barn stone since they have no deep footings
meanwhile, a smaller crew started installing the wood floor upstairs. what a nice view in that chop shop.
floor installation in the living room
later that day
day one progress on the dining room floor
meanwhile, the tile installer worked on the master shower floor